PAV10 cooling cabinet repair
Scheduled Maintenance Report for CAMRIS
Postmortem

This was part of an effort to get the SEP cabinet flow and filtering. The HUP group has placed a supplemental flow pump into the cabinet in the Pav10 holding area. The flow is now at the correct rate. The valve actuator on Siemens side was swapped out. The mechanical valve brass casing was not changed.

Posted Mar 13, 2024 - 09:43 EDT

Completed
The scheduled maintenance has been completed.
Posted Mar 08, 2024 - 09:59 EST
In progress
Scheduled maintenance is currently in progress. We will provide updates as necessary.
Posted Mar 08, 2024 - 08:00 EST
Scheduled
Siemens will replace a damaged valve in the cooling cabinet for PAV10. Scanning will not be possible during this time.
Posted Feb 29, 2024 - 14:56 EST
This scheduled maintenance affected: PAV10 (MRI Scanner).